Swim and Fitness Center renovation update

(Nov 17, 2011)

With the completion of the 13th week of the Swim and Fitness Center renovation project, the facility is starting to take on a new shape.

In the locker rooms, all plumbing is completed and the walls and floor are being covered with new tile. Drywall work and painting of the ceilings in the locker rooms is in progress. Next week, lockers will be installed, closely followed by sinks and fixtures.

The steam room is all but complete with exception of the light fixtures, door and most importantly, the steam generator. New cedar planks have been installed in the sauna with benches to come next week.

The hot tub tile and mechanical work are complete, and next week will bring a fresh coat of plaster to the main area of the hot tub.

New tile has been installed at the perimeter of all the pools.

Tile has also been installed on the floors in the lower lobby including the racquetball hallway and lower vestibule area.

The handicapped lift has been installed and surrounding walls are in the process of being completed.

All in all, the project is moving forward steadily.

If all continues to go well, an opening of early December is projected, but as always when doing construction, this date is subject to change.