In observance of Memorial Day, all work will be off the roadway or behind construction barriers and will not impact traffic. Work will not take place on Sunday, May 26, or Monday, May 27.

Approximately 1,000 cubic yards of concrete was poured this past week on the new Wadsworth Parkway bridge.

The second half of the deck pour will take place Wednesday, May 29, from 9 p.m. to 5:30 a.m. Eastbound and westbound U.S. 36 will be closed. Traffic will detour off of the roadway utilizing the on- and off- ramps.

The first portion of the bridge over the Burlington Northern Santa Fe tracks was demolished this week. The second phase of demolition is scheduled for early June.